Muscat: OQ announced the commissioning of one of Oman’s vital energy extraction projects, the OQ Liquefied Petroleum Gas (OQ-LPG) facility.
Built with a total investment of $826 million, OQ-LPG is the first of its kind gas treatment project in Oman to extract LPG and condensate from OQ’s Gas network.
With its centrepiece extraction facilities located in Salalah Free Zone adjoining the Port of Salalah, OQ-LPG has the potential to create a new energy hub in Salalah centring on the production of LPG, a commercially valuable and economically competitive fuel with growing demand in domestic and international markets.
While reiterating the position of Oman as an energy exporter, it will optimise the Sultanate’s gas value chain by recovering propane, butane and condensate for these markets.
The facility, built as per the highest standards in safety, quality, and technical integrity, consists of an extraction plant, a fractionation facility, storage tanks, shipping facilities, and an interconnection pipeline system. The plant will process approximately 8 million Standard Cubic Metres per Day (Sm3/d) of lean gas and will produce around 304-kilo tonnes per annum (KTA) of LPG products composed of 155 KTA of Propane (C3), 111 KTA of Butane (C4) and 38 KTA of Condensate (C5+).
Marking this important milestone, Sultan Ali Al-Burtumani, Vice President of Business Development OQ Downstream, stated “OQ-LPG plant is positioned as a strong contributor to the national economy through achieving the best utilisation of natural gas resources to extract liquefied gas. This will help in meeting the LPG needs of Dhofar governorate and southern Oman in general."
He added that OQ-LPG will further uplift our standards to provide better quality services for our clients and optimize stakeholder value. He pointed out that OQ is joining hands with the Ministry of Energy and Minerals to maximise the extraction of natural gas liquids (NGLs); the richer molecules within the nature for petrochemical industries developments.
OQ-LPG plant’s production is expected to reach a total of 300,000 metric tonnes (MT) per annum.
The plant holds immense potential in terms of revenue generation, In-Country Value (ICV) and community development. Besides deriving economic value through propane, butane and condensate sales, the plant will generate potential downstream business, such as petrochemicals.
During all its phases, the project has been promoting ICV in the gas sector as the project spent $260 million of ICV, with over 150 SMEs, 33 sub-contracts and Omani registered vendors.
OQ-LPG had several corporate social responsibility (CSR) initiatives in Dhofar including the supply of medical equipment to hospitals and building schools.
The commissioning of OQ-LPG, which is expected to be completed by mid-May 2021 forms the final technical requirement before the plant starts commercial operations.
The project team recently celebrated the production of the first on-spec product, which is considered one of the milestones during the commissioning phase.