Samail: Nama Water Services is actively working to implement water distribution network projects according to the highest quality standards and with high efficiency to meet the growing demand for water, which is driven by population growth and the urban and economic expansion witnessed across the Sultanate of Oman's governorates.

In this context, Nama Water Services continues the execution of the project to construct a water transmission line to Samail Industrial City and distribution networks for neighbouring villages. The completion rate for the project has reached 63 percent, with a total cost exceeding OMR12 million.