Muscat— Nama Electricity Distribution Company is continuing the implementation of a package of developmental and investment projects in Muscat Governorate within its 2026 investment plan, with a planned budget amounting to RO 22.47 million. The projects aim to raise the absorption capacity of the power grid and enhance its reliability and efficiency in line with population and economic growth and urban expansion across the governorate's various wilayats.
Eng. Mohammed Rashid Al Qari, General Manager of Major Projects at Nama Electricity Distribution Company, stated to Oman News Agency (ONA) that these projects come within the framework of the developmental plans implemented by the company to strengthen the infrastructure of electricity distribution networks, raise their operational efficiency, and improve the quality of services provided to subscribers, contributing to meeting the growing demand for electrical energy and supporting sustainable development in the governorate.
He added that the planned investment budget for Muscat Governorate for 2026 is distributed as RO 12.78 million for investment in medium-voltage (33 kV) networks, and RO 7.63 million for establishing new electrical networks at a voltage of (11/0.415 kV), in addition to RO 2.06 million for grid reinforcement projects at the same voltage.
He clarified that the volume of actual investment expenditure during the period from January to August 2026 amounted to RO 10.791 million, including RO 6.4 million for (33 kV) network projects, RO 4.06 million for establishing new networks, and RO 331,000 for grid reinforcement projects.
He affirmed that the company has completed executive works for several vital projects in the governorate, most notably the construction of primary substations in Sultan Haitham City at a cost of about RO 5.27 million, upgrading the Qurum substation at about RO 2.133 million, and upgrading the Al Hail North substation in the Wilayat of A’Seeb at RO 993,000, in addition to constructing the Wadi Ruwi substation with a capacity of (2×20 MVA) at an estimated cost of about RO 1.228 million.
He explained that projects that recorded a 100 percent completion rate and entered the closure phase include the Rusayl Industrial 1 substation project with a capacity of (2×20 MVA) at a cost of about RO 1.293 million, replacing electrical assets at the Azaiba South substation at RO 593,000, alongside constructing a new building, replacing (33 kV) switchgear equipment, and adding a ring main unit at the Muttrah stores at a cost of about RO 788,000, and a grid reliability enhancement project by adding a new (33 kV) electrical feeder in the Wilayat of A’Seeb at a cost of RO 155,000.
He pointed out the 100 percent completion of executive works for primary and secondary utility networks within the first phase of the Sultan Haitham City project up to September 2026, at an estimated cost of RO 2.792 million, in the context of providing electrical infrastructure for new urban projects.
Regarding projects under implementation, the General Manager of Major Projects stated that work is ongoing on constructing the Misfah substation in the Wilayat of A’Seeb with a capacity of (3×20 MVA) and at a cost of RO 2.396 million, where the completion rate reached 51.21 percent up to September 2026, alongside constructing a new substation in the Wilayat of Qurayyat with a capacity of (2×20 MVA) at a cost of RO 1.377 million and a completion rate of 56.3 percent.
He noted the continuation of construction works on the Al Ansab Heights substation project in the Wilayat of Bawshar at a cost amounting to RO 2.078 million and a completion rate reaching 85.4 percent, in addition to the Yiti substation upgrade project in the Wilayat of Muscat at an estimated cost of about RO 1.747 million and a completion rate of 5 percent up to September 2026.
He mentioned that the project to supply (11 kV) electrical capacitor banks for several primary substations in Muscat Governorate has entered the testing and commissioning phase with a completion rate of 95 percent and at a cost of RO 593,000, to contribute to improving grid performance and raising its operational efficiency.
In the context of future projects, Eng. Mohammed Rashid Al Qari explained that the company is currently completing the preparatory and design phases for several projects, including constructing the Al Shabri substation in the Wilayat of A’Seeb at a cost of about RO 2.193 million, the Al Maabilah South substation at a cost of RO 2.501 million, and constructing a new substation in the Wilayat of Bawshar with a capacity of (2×20 MVA) at a cost of RO 2.32 million, in addition to a project to replace transformers at the Al Falaj substation in Ruwi at an estimated cost of about RO 450,000.
He concluded his statement by affirming that Nama Electricity Distribution Company is pressing ahead with completing its projects according to approved schedules and in observance of the highest standards of quality and operational safety, noting that these investments enhance the grid's readiness to absorb future energy demand and support the developmental, urban, and economic march across the wilayats of Muscat Governorate.